PrerequisitesBefore calculating:
- Active BOMs: For all products (e.g., Onina Tissue BOM with pulp, adhesive, packaging).
- Accurate Stock: Update raw material quantities in
Stock > Stock Balance. - Substitutes: Define alternates (e.g., Yeast-Brand-B for Valdana Bread).
1.0 Overview
Material Requirements Planning (MRP) calculates total raw materials needed based on:- Production Quantity (e.g., 5,000 Valdana Bread loaves)
- Bill of Materials (BOM)
- Current Stock Levels
- Planned Substitutions
2. 0 Step-by-Step Calculation
2.1 Generate Production Plan- Go to:
Manufacturing > Production Plan > New - Fill in:
- Item: Finished product (e.g., Luca Engine Oil 5W-30)
- Quantity: Production target (e.g., 1,000 liters)
- Use Multi-Level BOM: ✓ Check if using sub-assemblies
- Get Raw Materials:
- System auto-calculates requirements based on BOM.
2.2 Review Material Requests
- Raw Materials Table shows:
- Required Qty: Total materials needed (e.g., 950L base oil for 1,000L Luca Oil)
- Available Qty: Current stock
- Additional Qty: Shortfall to procure
- Consider Substitutes:
- If Additive-X is low, system suggests Additive-Y (if defined as alternate).
2.3 Adjust for Waste/Scrap
In BOM settings:- Set Scrap % for loss-prone materials:
- Example: 5% scrap rate for Ovita Water caps → system adds extra 5% to requirement.
3.0 CGIC Product Examples
Valdana Bread (1,000 loaves)
| Material | BOM Qty/Loaf | Total Required | Available | To Order |
|---|---|---|---|---|
| Flour | 0.5 kg | 500 kg | 300 kg | 200 kg |
| Yeast | 0.02 kg | 20 kg | 5 kg | 15 kg (or Yeast-Brand-B) |
| Sugar | 0.1 kg | 100 kg | 120 kg | 0 kg |
Ovita Waters (5,000 bottles)
| Material | BOM Qty/Bottle | Total Required |
|---|---|---|
| Bottles | 1 | 5,000 |
| Caps | 1 | 5,000 (+5% scrap = 5,250) |
| Purified Water | 0.5L | 2,500L |